FAQ for entrusting the work of upgrading and implementation of the electrical system serving the exhibition area “GNAM VILLAGE”

THE FAQ.

Question: In order to be able to demonstrate economic and financial capacity (Art. 83(1)(a) Legislative Decree No. 50/2016), you require turnover for the three-year period 2013/2015.
But if the invitation is dated 09/01/2017 and the tender is to be held on 23/01/2017, the three-year reference period should be (2014/2016).

Response: as the date of the letter of invitation is 9/1/2017, the previous three years means the one that should already be properly filed (2013/2015), the 2016 budget at the time of bidding delivery and execution of work is not available in its final forms.

question 2:

we ask your administration for clarification regarding the work of adjustment and implementation of the electrical system serving the exhibition area “GNAM VILLAGE “
– In point 1 of the special tender specifications there are written all the work to be done,in particular it is asked for the work of ” laying of a new supply line from the cavea or,or alternatively,from the point of delivery of the supply located in the electrical substation,to the GNAM space for a development of about 300 ml as per the graphic Attachment B”
THE SUPPLY OF CABLES FOR THIS WORK IS NOT PROVIDED FOR? ONLY THE LAYING HAS TO BE DONE?

answer 2:

the supply of cables is absolutely included, as well as all supplies and works to realize the finished work in a workmanlike manner