FAQs, notices, etc. – Corporea computer network activation
“Provision of goods and services for the activation of Corporea’s new computer network and technology upgrade of active equipment.”
FAQ
Question 1: When filling out Annex 3, according to point A.6 of the letter of invitation to the negotiated procedure, is it necessary to indicate the name and details of the subcontractor, if any?
Answer: It is not mandatory.
Question 2: Access Switches: in the technical specifications you refer to supporting PoE functionality but in the port description there is no reference to PoE. Therefore, you are asked to make explicit whether the Access Switches should also have PoE ports.
Answer: Access switches must also have PoE ports.